Use My Paypal To Buy Uggs

and here we go again ...

After two weeks very quiet work has finally resumed this week on the job.

MONDAY:
You've probably noticed on the last picture but a wooden fascia board had completed the bottom of the frame. We chose a PVC finish white over it.

all right for the setting until it is horizontal but where it gets complicated is the bow window. And yes! cut at 45 ° and the slope of the breakwater .... hard drive. The carpenters will need to try several times to pass a result rather "bof-bof " to "can do better ':

As expected, missing five rows of bricks to close the angles of the bow window. It seemed more logical that the masonry is done in the wake before laying the tiles, and it is done on Monday. Although this area is very accessible, I admit being disappointed by finishing edges far too coarse relative to the rest of the work:

the way, he will redo the fascia.

the same time part of the eavestrough and are asked

WEDNESDAY:
pallets of tiles are delivered, we discover our "storm glossy 44"

We hasten to put them in touch with the bricks but very difficult to give an opinion because the record of the tile depends immensely from his angle and brightness.

THURSDAY:
The roofers have been introduced and have already placed bituminous felt on nearly every surface:


FRIDAY:

that advance to the super fast the bedding, the laying of the tiles is imminent.

The fascia has been very well restored in the level of cuts, but it does not fully cover the arrest of bricks, there is a hole and some are loosened! Will we get there?